Project Brief
A cable crossing over the River Colne and Colne Brook was required to connect a Data Centre to Iver Substation.
Key Project Deliverables
- Bridge-mounted and Horizontal Directional Drilling (HDD) methods were ruled out, leaving open-cut excavation as the only option
- Works were completed in 21 days following two years of planning and ecological safeguards