Freedom Group – Virtus 11kV cable installation

Freedom Group – Virtus 11kV cable installation  

January 15th, 2018

 

Please be advised that JSM will be excavating a trench a trench for Electricity supply on behalf of Freedom in the public highway past or to the rear of your business/property as part of network expansion. The works will normally take place between the hours of 8am – 6pm Monday to Friday and will include weekends (Sat 8 am – 6 pm and Sunday 9 am – 6 pm), to ensure the works proceed as quickly as possible.

here will be a requirement for no parking outside of your property whilst this essential work is completed and areas will be highlighted with no parking zones.

We expect disruption directly outside your property will be a maximum of 5 days.

The cable route to be constructed from the substation on High Road to Prologis Park on Horton Road. This work was carried out with the permission of the Local Authority’s Highway Department, the Traffic Police and is in strict accordance with the New Roads & Street Works Act.

 

Works will be taking place within the following roads

 

  • High Street
  • Falling Lane
  • Otterfield Road
  • Fairfield Road
  • Yew Avenue
  • Colham Avenue
  • Providence Place
  • Whitehorn Avenue
  • Horton Road

 

 

The next phase of the construction will take place between the months of March and April and will involve cable installation and Jointing via standard methods.

On completion of the duct installation, we will return to site to install the cable and Joints   Due to the extensive nature of the scheme it is not possible to confirm the ongoing programme now, but should you require further information over the coming months please do not hesitate to check the website for the project.

 

Project Route Map

Letter Drop