Project Brief
The Network Operator required the safe removal of redundant oil filled 132kV cables from their Westcombe Park site in Deptford.
Key Project Deliverables
- Two joint bays and 460m of a 132kV circuit were removed and new usable 160mm SDR11 duct was installed
- NICE method was employed which enabled safe, trenchless extraction