Redundant 132kV oiled filled cable route removal

Locations: Greenwich, UK

Project Brief

The Network Operator required the safe removal of redundant oil filled 132kV cables from their Westcombe Park site in Deptford.

Key Project Deliverables

  • Two joint bays and 460m of a 132kV circuit were removed and new usable 160mm SDR11 duct was installed
  • NICE method was employed which enabled safe, trenchless extraction

Project Categories

Network Operator