PROJECT BRIEF
The Network Operator required the safe removal of redundant oil filled 400V cables in Ross-On-Wye.
KEY PROJECT DELIVERABLES
- JSM removed a 1.98km section of redundant 400kV oil-filled cable
- NICE method was employed which enabled safe, trenchless extraction
- Recovered cables were sealed and transported for recycling