Bridgwater Gigafactory

Building to meet the requirements for a new Gigafactory in Bridgwater.

Project Overview

Project Detail
Design and build for a new 33kv electrical connection (approx. 9km) between the new Agratas Gigafactory and National Grid / National Grid Electricity Distribution (NGED) Bridgwater Substation. The works will take place in two phases for minimum disruption; Phase 1 - Civils duct installation Phase 2 - HV cable installation.
Duration
11 months
Estimated Completion
June 2025

Live Updates

LS
Roads on cable route
08 July 2024
08 July 2024
A372 Westonzoyland Road, Bower Lane, Little Sydenham Farm Road, Old Bath Road, A39 Bath Road, A39 Puriton Hill, Hillside & Enterprise Way.