Gas Upgrade 037

Project Detail

JSM Group Services Ltd. are a trusted Utility Infrastructure partner working on behalf of Southern Gas Networks (SGN) to deliver Gas upgrade 037.

Live Updates

Works update | 23 October 25

We anticipate that all our works will be completed weekending 15 November 2025.

W/C 27 October 25, there will be 4-way traffic lights installed on Northey Avenue junction with The Avenue, for the team to carry out an open cut trench to install approximately 80m of 90mm pipe, for reinforcement.

Note that there is currently another gas contractor carrying out works on the north side of Northey Avenue.

State of works

 

Project Manager:
gas.upgrade037@jsmgroup.com

Proposed phase of works | 23 January 25

Project SOE12863 Sandy Lane

Programme of works Team 1 Sandy Lane Team 1

Programme of works Team 2 Sandy Lane Team 2 Push Plan

Programme of works Team 3 Sandy Lane Team 3 NEW Push Plan


Project Manager:
gas.upgrade037@jsmgroup.com

What do I do if I can smell gas?

  • Call the National Gas Emergency Number 0800 111 999
  • DO Open windows & Doors
  • DON’T smoke or use any naked flames
  • DO Turn off the gas supply at the gas meter
  • DON’T Touch and electrical switches
  • DO Call 0800 111 999 – Lines open 24 / 7