Arla Dairies

JSM as the Principal contractor undertook this contract for the installation of 2 x 3 33kV cables and 2 x pilot cables routed from Aylesbury East grid sub-station to the proposed Arla Dairy site located at College Road, Aston Clinton.

The installation works totalled 5.6km and included a directional drill under the Grand Union Canal and a major road crossing traversing the A41.

The size of the trench for an element of the works at least needed to be increased to accommodate a 315mm gas main to be installed by another contractor.